EP28 Gentilino–Lamone: the project enters a new operational phase
23/01/2026
The EP28 – Lot 202 project continues to move forward at a steady pace. By the end of 2025, CSC Costruzioni (Webuild Group) completed phases 3A and 3B of the north–south carriageway, from km 30+120 to km 26+950, delivering 3,170 metres of infrastructure and laying 55,000 tonnes of asphalt.
👉 2026 will mark a key milestone with the launch of phases 4A and 4B:
- completion of the north–south carriageway up to km 23+950 (around 3,000 m)
- start of works on the south–north carriageway, in flat sections and the central reservation
📦 Planned quantities: 74,000 tonnes.
📈 In 2027, production is expected to reach around 71,000 tonnes, confirming the project’s high output levels.
👷♂️ Works are carried out while ensuring full operability of the N2 motorway, with a strong focus on execution quality, planning, and safety.
♻️ Sustainability also plays a central role, through the use of materials and technical solutions aimed at reducing environmental impact.
A strategic project for Canton Ticino, showcasing our teams’ ability to turn complexity into tangible results.